SUMMARY:Function tests on UPS and emergency power systems in NBG1-DC1
DTSTAMP:20260402T043300Z
DTSTART:20260401T143000Z
DTEND:20260402T043300Z
DESCRIPTION:We will do routine function tests on our UPS systems and on our emergency power system. Due to the redundant design of our power supply systems\, we do not expect any issues.\n\nhttps://status.hetzner.com/incident/87585d57-b663-4e87-9e9f-893ea217d670